10MW Solar Power Project in Darkhan City

Representative Participant
Sharp Corporation
Partner Participant: Solar Power International LLC (SPI)
Host Country
Mongolia
Selected Year
2015
Type
JCM Model Project
Sector
Renewable Energy
Registered
Credit issued
Active

Outline of GHG Mitigation Activity

The project aims to reduce CO2 emissions by constructing a 10MW Solar Power Generation Plant beside the 110kV substation in Darkhan City, which locates approximately 230 km North of the capital city Ulaanbaatar, and supplying the generated electricity through the power transmission network.

The power plant employs crystalline solar modules of maximum output of 310W per panel and module conversion efficiency of 15.9%. Approximately 32,000 numbers (72 series) of these modules and peripheral systems are installed on a land of 36 ha.

Expected GHG Emission Reductions

11,221 tCO2-eq./year

= PV generation (a)
    × Reference emission factor (b)
= 14,079 [MWh/year] × 0.797 [tCO2/MWh]

Site of JCM Project

Related photos

  • Gallery

  • Gallery

JCM Methodology

Methodology No. Title Methodology Proponent
MN_AM003 Ver2.0 Installation of Solar PV System Institute for Global Environmental Strategies

Progress

JCM Project Registration

Reference No. Project Title Registration Date
MN004 10MW Solar Power Project in Darkhan City 04 Dec 2017

Issuance of credits

Reference No. Monitoring Period Date of JC decision on notification Amounts of Credits Issued
MN004 01 Jan 2017 - 31 Jul 2017 24 Oct 17 8,947