Introduction of 2MW Rooftop Solar Power System to Non-ferrous Metal Factory

Representative Participant
The Kansai Electric Power Company, Incorporated
Partner Participant: Kansai Energy Solutions (Thailand) Co., Ltd.
Host Country
Thailand
Selected Year
2021
Type
JCM Model Project
Sector
Renewable Energy
Not registered
Active

Outline of GHG Mitigation Activity

2 MW Solar Power System is installed on the rooftops of a non-ferrous metal factory, and all the generated power is consumed by the factory.
By replacing a part of the grid electricity with solar power, the greenhouse gas (GHG) emissions are reduced.

Expected GHG Emission Reductions

947 tCO2-eq./year

= (Reference CO2 emissions)
– (Project CO2 emissions)

・ Reference CO2 emissions
= (Quantity of the electricity generated by the project) [MWh/year]
×Emission factor [tCO2 /MWh]
・ Project CO2 emissions
= 0 [tCO2 /year])

Site of JCM Project