Improvement of Thermal Insulation and Water Cleaning/Air Purge at Power Plant

Representative Participant
Kanden Plant Co., Inc.
Host Country
Mongolia
Selected Year
2013
Sector
Energy Efficiency

Outline of GHG Mitigation Activity

Energy efficiency at Combined Heat and Power Plants #3 and #4 (CHPs 3 & 4) will be improved by using following technologies:
 1) improvement of thermal insulation by using “Eco-AIM (e’-AIM) Method”, and
 2) advanced maintenance of heat exchangers by using “Rakuchin Gun Device”.

Expected GHG Emission Reductions

3,000tCO2/yr for both CHPs 3 & 4
 ←CHP-3: 950tCO2/yr
  ←Insulation: 935tCO2/yr, and
  ←Cleaning: 15tCO2/yr
 ←CHP-4: 2,050tCO2/yr
  ←Insulation: 2,035tCO2/yr, and
  ←Cleaning: 15tCO2/yr

Site of JCM Project

CHP-3&CHP-4 to be carried out in this project is located on the suburbs of Ulanbaatar.