49MW Solar Power Project in An Giang Province
- Representative Participant
- Kanematsu KGK Corp.
Partner Participant: SAO MAI GROUP CORPORATION
Not registered
Active
Outline of GHG Mitigation Activity
Greenhouse gas (GHG) emissions are reduced by introducing a 49MW solar power plant at 54.7ha (547,000m2) project site in An Giang Province. The generated electricity is suppled to the grid.
This project contributes to the target of Vietnam Government to have 23% of renewable energy from the total electricity supply in Vietnam by 2030.
Expected GHG Emission Reductions
24,570 tCO2-eq./year
= (Reference CO₂ emissions)
– (Project CO₂ emissions)
= ((Quantity of the electricity generated by the
project ) [MWh/year] – 0 [MWh/year])
×Emission factor [tCO₂ /MWh]
Site of JCM Project
JCM Methodology
Methodology No. | Title | Methodology Proponent |
---|---|---|
VN_AM007 Ver1.0 | Installation of Solar PV System | Institute for Global Environmental Strategies |