Energy saving by co-generation project in the fiber factory
- Representative Participant
- The Kansai Electric Power Co., Inc.
Outline of GHG Mitigation Activity
High efficiency gas fired cogeneration plant will be introduced at the fiber factory located in Thailand. In this factory electricity is supplied from the regional grid and steam is supplied from the coal fired auxiliary boiler.
In addition, various methods to increase energy efficiency will be introduced in the utility facilities.
Expected GHG Emission Reductions
Around 20,000 t-CO2/year
Reference emissions: 61,180 t-CO2/year
1) Displacing electricity supplied from the regional grid: 47,040 t-CO2/year
2) Displacing steam generated by the coal fired auxiliary boiler: 14,140 t-CO2/year
Project emissions: 40,841 t-CO2/year