43MW Solar Power Project in Kakheti and Kvemo Kartli Regions
- Representative Participant
- Sharp Energy Solutions Corporation
Partner Participant: LLC Mzis Veli, LLC Kakhetis Mze
Not registered
Installing
Outline of GHG Mitigation Activity
This project introduces solar power generation facilities with a total capacity of 43MW (31MWx1site + 2MW x 6 sites) in the regions of Kakheti and Kvemo Kartli, near the Tbilisi city.
Electricity generated is sold either to the national grid or on the spot market.
This project reduces greenhouse gas (GHG) emissions by replacing part of the electricity from the fossil fuel-derived grid power with renewable energy.
Expected GHG Emission Reductions
21,501 tCO2-eq./year
= Reference CO2 emissions [tCO2/year]
– Project CO2 emissions [tCO2/year]
・ Reference CO2 emissions [tCO2/year]
= (Quantity of the electricity generated by the project) [MWh/year]
× Emission factor [tCO2/MWh]
・ Project CO2 emissions
= 0 [tCO2/year]
Site of JCM Project