10MW Solar Power and 3MWh Storage Battery Project in Pursat Province
- Representative Participant
- The Chugoku Electric Power Co., Inc.
Partner Participant: SchneiTec Co., Ltd., SchneiTec Zealous Co., Ltd.
Not registered
Outline of GHG Mitigation Activity
This project introduces a 10MW solar power + 3MWh battery energy storage system (BESS) in Pursat Province. The generated electricity smoothens short-term fluctuations of solar power by BESS and is sold to Electricité du Cambodge (EDC), the national grid.
This project reduces greenhouse gas (GHG) emissions by replacing part of the electricity from the fossil-fuel based grid power with renewable energy.
Expected GHG Emission Reductions
7,975 tCO2-eq./year
= Reference CO2 emissions [tCO2/year]
– Project CO2 emissions [tCO2/year]
・ Reference CO2 emissions [tCO2/year]
= 22,594 [MWh/year] × 0.353 [tCO2/MWh]
・ Project CO2 emissions
= 0 [tCO2/year]
Site of JCM Project