20MW Solar Power Project in Krakor, Pursat Province
- Representative Participant
- MinebeaMitsumi Inc.
Partner Participant: Minebea (Cambodia) Co., Ltd. , Minebea SchneiTec Green Power Co.,Ltd.
Not registered
Outline of GHG Mitigation Activity
This project introduces a 20 MW ground mount solar power plant in Krakor, Pursat Province. The generated electricity is sold to Electricite de Cambodge (EDC), the national grid.
This project reduces greenhouse gas (GHG) emissions by replacing part of the electricity from the fossil fuel-derived grid power with renewable energy.
Expected GHG Emission Reductions
14,135 tCO2-eq./year
= Reference CO2 emissions [tCO2/year]
– Project CO2 emissions [tCO2/year]
・ Reference CO2 emissions [tCO2/year]
= (Quantity of the electricity generated by the project) [MWh/year]
× Emission factor [tCO2/MWh]
・ Project CO2 emissions
= 0 [tCO2/year]
Site of JCM Project