Introduction of 1.2MW Rooftop Solar Power System to Electronic Equipment Assembly Factory (JCM Eco Lease Scheme)

Representative Participant
Tokyo Century Corporation
Partner Participant: KATOLEC PHILIPPINES CORPORATION; BPI Tokyo Century Rental Corporation
Host Country
Philippines
Selected Year
2023
Type
JCM Model Project
Sector
Renewable Energy
Not registered
Installing

Outline of GHG Mitigation Activity

This project reduces greenhouse gas (GHG) emissions by installing a 1.2 MW photovoltaic system on the roof of a Japanese manufacturing plant for self-consumption purpose.

The JCM Eco Lease scheme, which combines financing programme and leasing, reduces initial installation costs.

Expected GHG Emission Reductions

697 tCO2-eq./year

= (Reference CO₂ emissions) [t CO₂/year]
– (Project CO₂ Emission) [t CO₂/year]
・ Reference CO₂ emissions
= (Quantity of the electricity generated by the project) [MWh/year]
×Emission factor [t CO₂/MWh]
・ Project CO₂ emissions
=0 [t CO₂/year])