Introduction of 1.53MW Rooftop Solar Power System in Auto Parts Factories

Representative Participant
Tokyo Century Corporation
Partner Participant: Enomoto Philippine Manufacturing, Inc. / Aikawa Philippines, Inc.
Host Country
Philippines
Selected Year
2017
Type
JCM Model Project
Sector
Renewable Energy
Registered
Active

Outline of GHG Mitigation Activity

This project is to install 1.53MW solar panel on the rooftop of the Enomoto Philippine’s factory and the Aikawa Philippines’s factory in the south of Manila. Electricity generated by solar system is used for their power-consumption and reduce CO2 emissions by displacing part of grid electricity.

Expected GHG Emission Reductions

1,061 tCO2-eq./year

= (Reference CO2 emissions) [tCO2/year]

       – (Project CO2 Emission) [tCO2/year]

= ((Reference Power consumption) [MWh/year]

     – 0 [MWh/year]))×Emission Factor [tCO2/MWh]

Site of JCM Project

JCM Methodology

Methodology No. Title Methodology Proponent
PH_AM002 Ver1.0 Installation of Solar PV System Institute for Global Environmental Strategies

Progress

JCM Project Registration

Reference No. Project Title Registration Date
PH002 Introduction of 1.53MW Rooftop Solar Power System in Auto Parts Factories 04 Nov 21