30MW Solar Power and 11MWh Storage Battery Project in Krakor, Pursat Province

Representative Participant
MinebeaMitsumi Inc.
Partner Participant: Minebea (Cambodia) Co., Ltd. , Minebea SchneiTec Green Power Co.,Ltd.
Not registered
Installing

Outline of GHG Mitigation Activity

This project introduces a 30 MW ground-mount solar power plant equipment with a 11MWh storage system in Krakor, Pursat Province. The generated electricity is sold to the state-owned power company, Electricite de Cambodge (EDC).

This project reduces greenhouse gas (GHG) emissions by replacing part of the electricity from the fossil fuel-derived grid power with renewable energy.

Expected GHG Emission Reductions

21,423 tCO2-eq./year

= Reference CO2 emissions [tCO2/year]    
  – Project CO2 emissions [tCO2/year]

 

 ・ Reference CO2 emissions [tCO2/year]
   = (Quantity of the electricity generated by the project) [MWh/year]
     × Emission factor [tCO2/MWh]
 ・ Project CO2 emissions
   = 0 [tCO2/year]

Site of JCM Project