Introduction of Amorphous High Efficiency Transformers in Power Grid

Representative Participant
Yuko Keiso Co., Ltd.
Partner Participant: Electricite Du Laos
Host Country
Lao PDR
Selected Year
2017
Type
JCM Model Project
Sector
Energy Efficiency
Registered
Active

Outline of GHG Mitigation Activity

The purpose of this project is to reduce CO2 emission through the introduction of amorphous high efficiency transformers instead of transformers with silicon steel core in power grid.

1,307 transformers in total are introduced to Electricite Du Laos.

The use of amorphous alloy in the amorphous transformer’s iron core leads to improvement of electrical characteristics and significantly reduces non-load losses (standby electricity).

Expected GHG Emission Reductions

2,109 tCO2-eq./year

= (No load losses of the reference transformer – No load losses of the project transformer) x

(1 – Blackout rate during the project period) x CO2 emission factor of the grid

Site of JCM Project

Amorphous high efficiency transformers are introduced into all regions in Laos (17 provinces and one city)

JCM Methodology

Methodology No. Title Methodology Proponent
LA_AM003 Ver1.0 Installation of energy efficient transformers in a power distribution grid Institute for Global Environmental Strategies

Progress

JCM Project Registration

Reference No. Project Title Registration Date
LA004 Introduction of Amorphous High Efficiency Transformers in Power Grid 24 May 23