14MW Solar Power Project in Vientiane Province and Borikhamxay Province

Representative Participant
Kayama Kogyo Co., Ltd.
Partner Participant: NAWADEE GREEN ENERGY Co.,ltd
Host Country
Lao PDR
Year
2020
Type
JCM Model Project
Sector
Renewable Energy
Not registered
Installing

Outline of GHG Mitigation Activity

This project installs photovoltaic (PV) power generation systems to supply the generated electricity to Electricité Du Laos (EDL).

Project sites (Total 14MW) :
Site1: Namak Village, Thoulakhom District, Vientiane Province (5MW)
Site2: Mai-Sanesamlan Village, Pakading District, Borlikhamxay Province: (4.5MW)
Site3: Phonsy-Phonxay Village, Pakading District, Borlikhamxay Province: (4.5MW)

This project contributes to stabilize electricity supply in Lao PDR and to reduce greenhouse gas (GHG) emissions by using renewable energy.

Expected GHG Emission Reductions

8,030 tCO2/year

= reference CO2 emissions
 - project CO2 emissions

 ・Reference CO2 emissions
  = Quantity of the electricity generated by the project [MWh/year]
   x Emission factor [tCO2/MWh]

 ・Project CO2 emissions
  = 0 [tCO2/year]

Site of JCM Project